Development Stories

Works recently completed in District Patiala :

  • S/R/ to Devigarh Naneola Road (PIDB Funded) with a amount of Rs. 312.93 lacs.
  • Construction of 30 Beded Community health Centre Dudhan Sadhan at Patiala with a amount of Rs. 530.00 Lacs.
  • In Ordinary repair programme 2016-17, the length of 9.08 km of Plan Roads repaired with the amount of 35.00 lacs.
  • Construction of ROB 15 C at Patiala, Rajpura, Bathinda Section on Northern Bye Pass Patiala with a amount of Rs. 1997.00 lacs.
  • Construction of Catle Breeding Farm at Rauni at Patiala with a amount of Rs. 3948.87 lacs.
  • Construction of Sewa Kendras (31 Nos. Type-II & 112 Nos. Type-III) = 143 Nos. with a amount of 2851.53 lacs.
  • Upgradation of Patiala to samana-Guhla road via Dakala, Karhali Sahib, Nizamniwala & Kamalpur RD 12.00 to 25.80 = 13.80 Km. 2015-16, the length of 13.80 km of Link Roads repaired with the amount of Rs.591.77 lacs.
  • Upgradation of Patiala Pehowa Road (SH-8) RD 18.00 to 36.50 2015-16, the length of 18.50 km of Link Roads repaired with the amount of Rs.1931.68 lacs.

Works is in Progress in District Patiala.

  • Construction of Type 332 No. Quarters, Near Ghalouri Gate at Patiala under OUVGL Scheme-i is in progress (84% work completed) with a amount of Rs. 2896.38 lacs.
  • Construction of Boys Hostel in Govt. Medical College Patiala is in progress (77% work completed) with a amount of Rs. 154.52 lacs.
  • Construction of Girls Hostel in Govt. Medical College Patiala is in progress (91% work completed) with a amount of Rs. 270.69 lacs.
  • Construction of Labs for Physiology Department in Govt. Medical College Patiala is in progress (91% work completed) with a amount of Rs. 54.40 lacs.
  • Construction of Admin. Academic, Workshop & Hostel Block in College of Aeronautical Engineering at Patiala is in progress (57% work completed) with a amount of Rs. 650.83 lacs.
  • Widening, and Strengthening of Patiala Bhadson Road R.D 8.00 Km to 11.00 Km =(3 Km) (width 5.50 mtr to 9.00 mtr including 1m wide paved shoulder on both side) under CRF scheme (90% work completed) with a amount of Rs. 385.39 lacs.
  • Repair of 1 No. Critical Road G.T. Road to Shambhu Ghanour Road via Jand Mangoli & Lachhru Kalan (Section Kami Khurd to Bapror) having length 9.00 km (35% work completed) with a amount of Rs. 125.09 lacs.
  • Construction of Sub-Tehsil Complex Building at Ghanour is in progress (92% work completed) with a amount of Rs. 120.42 lacs.
  • Upgradation of Bahadargarh Seel Ghanour Shambhu Road having a length of 28.00 km under CRF scheme (12% work completed) with a amount of Rs. 5256.83 lacs.
  • Construction of Study Centre at Vill. Bhanri, Tehsil Samana is in progress (14% work completed) with a amount of Rs. 377.26 lacs.
  • Strengthening of Patiala-Gulha-Cheeka Road having a length of 23.20 km under CRF scheme (92% work completed) with a amount of Rs. 1498.92 lacs.
  • Repair of 1 No. Critical Road S/R of Link Road Khanouri Arno Road to Sagra (Section Khanouri to Gurunanakpura Kangthala Taipur Chandhera, Behar Sahib. having length 9.30 km (70% work completed) with a amount of Rs. 99.92 lacs.

Note:- Contents are provided by respective office/departments as on date 14/06/2017.